How to Build Basement Stairs
Step 3 of 9

Clip 1/3
Helpful?
Step 3 · Install Top Support for Stringers
At the top of the stair opening, where the stringers will meet the upper level, install a strong support. This can be a pressure-treated ledger board bolted to the subfloor and rim joist, or solid wood blocking installed between the joists. Ensure this support is exceptionally strong as it will bear a significant portion of the stair's load. The ledger board should be level and flush with the edge of the opening where the stringers will sit.