How To Manage A Construction Project At The Beginning
Video by Jason Schroeder · 1 moment used in Oak Valley Designs's DIY guides · 9:38 long

Moments in this video
- 0:40–2:58 Manage Long-Lead Procurement
From How to Plan a Stair Remodel Budget and Sequence, Step 6: Plan for Material Procurement and Delivery
It is critical to identify and initiate the procurement process for any materials or equipment that have extended delivery times. Examples include switchgear, air handlers, curtain wall systems, specialized tiles (e.g., from Italy), and elevators. These items must be secured and scheduled for delivery before their respective construction activities commence. This pre-planning, often occurring three months before the actual project start, is facilitated by using macro-level and norm-level takt plans (master schedules) to 'trigger' the buyout process when necessary, ensuring components are on-site precisely when installation is due.
The guide that use this video
Transcript
0:02 how to manage a construction project at the beginning in this video I'm going to talk to you about the key considerations that we must know about when we're starting a project and really attempting to manage it and the risks that we really need to look out for if you want to have a great perspective of what running a project at the beginning is all about then stay with us on this [Music] video okay everybody I am super stoked to talk to about this concept I love this been through this many different times and I want to give you an overall perspective let me go ahead and head over here to my flip chart and we're going to have some fun okay so first and foremost let's say that this right here is your start date on your project you really want to get these first
0:48 mobilization foundations excavation these activities like really going well and you want to come out of the gate really hitting it hard really going fast now you know me I'm not a p sure I'm a driver but if we want to drive 80 M an hour at the beginning of the project is the time to do it later on in the project when you have 40 different trade Partners it's hard to speed up or slow down without massive consequences but when you have a couple of Trades here at the beginning we must get out of the gate fast so what I want to say is about 3 months before you start the actual project we had better be to a spot where the builders are involved and we have our macro level T plan which means our master schedule and our Norm level tack plan we'd better be looking at long lead
1:35 procurement right so before we start if you have Shoring if you have post tension systems if you have complex reinforcing types if you have anything that you need to start this building you better have managed the long lead procurement before we come to that stage so that's why I love preconstruction efforts is because you can go ahead and get deferred submittals for the post tension out you can get your detailing for your concrete structure going you can get your showing systems designed and get those shop drawings going through and get them approved right anything that you need here needs to be done in preconstruction so one of the first things that we need to look at is procurement right do we have long lead procurement items coming on the way for the things that we need so let's check
2:20 it out obviously you're going to have switch gear obviously you're going to have air handlers if you have curtain wall on your project unitized curtain wall on your project you're going to have to get that out if you have tile from Italy anything that's long lead elevators needs to be taken care of in preconstruction and the way that I like to do this is if you have a macro or Norm level tack plan meaning your production plan you work those back and you trigger those you start the buy out in the procurement process when it's needed so you can start right here so if you want to know how to really manage a construction project early on make sure that you're managing procurement in a remarkable way the other thing that I want to point out is is temporary utilities this is something that I always freak out about and I think we don't take this seriously enough so if
3:06 we're going to grade the site what's the first thing that we need water right so we need to know where are we going to get the water source from where are we going to tie into what's the permitting process do we have the actual infrastructure to bring it over do we have the contractor to pull the permits right we need water to the site we also have dry utilities right we have the communications so your internet and we have temporary power for your project site if you're not going to use generators so when I talk about temporary utilities I want to make sure that you have your water and then you might not need temporary power right away maybe you need temporary power before you start your foundations I want to make sure that you have both of these tracking properly so that you have them on time and most of the time your trade
3:51 partners are going to be experts at this so you'll have to make sure that your bidding process in your buyout gets you a site utility contractor or a plumber and then your electrician so that you're good to go and you can do the power drop and then bring the temporary power to your locations on site so these are the key things that I'm always looking for now one other thing here with this in addition to Temporary utilities we have permanent utilities that might be in the way you've heard me talk about in preconstruction that if you have a duct Bank in the way Communications cabling if you have gas lines in the way sometimes it takes quite a bit of time to move those out of the way I remember two scenarios from working here in Phoenix one was a duck bank that APS had to move out of the way and this was Fast 5 months to get that relocated out of
4:38 the way of the building and then we had 100 Pair cable for the communications line that needed to be moved out of the way I think it was by sentury link and that took about 3 months to move out of the way and if we hadn't seen those things we would be in trouble so make sure you get any permanent utilities out of your way and any temporary utilities to the project site by the time you need to start otherwise it's going to be a big deal the other thing that I want to talk to you about is survey one of the things that we need to do I won't go into it in too much detail but if you have a project site every project site will have basis of bearings which will be your coordinates and your benchmark these are The Monuments the city monuments that they use to as belt the site right you need to identify a northing easting and elevation for these
5:26 and then you need to actually understand the coordinates for the building right for some reason in this industry the survey company and the civil engineers still don't provide this information and you have to beg for this information I have no idea why we should get this right out of the gate so that you can go ahead and Traverse the site for your primary control through your basis of earings and then design your grid system and come in here and lay out your secondary control right for the building so survey is a huge consideration and I'm telling you at least 6 weeks before your ntp date you need to be working on that and you probably need to consider having your field Engineers out here surveying and doing this traversing and level looping 2 weeks before you break
6:12 ground the fourth thing that I want to talk to you about it's actually the sequence but really if you like this content if you're finding this valuable please like this video subscribe comment below unless the video is like hidden in the hundreds that we have and a year old I respond to them personally so we'd love to hear from you but really item number four is sequence the work for a quick mobilization here's what I want to say all of these trades in here even though they're not on the site you want to go ahead and do a pull plan as soon as you have them available you'll want to work through this you'll want to make sure that you have the fastest possible mobilization and in most cases when you actually get here on site you're going to have to do what I call a day by day or a week by week analysis that means you do a drawing you say hey week one
6:59 and then you do a drawing right and you show what that looks like week two and then you do a drawing and you see what that looks like and then week three and then you do a drawing and see what that looks like a week by week or day byday analysis to make sure that everybody's in the right spot that we're getting grading to the first pad we're certifying that first pad utilities aren't in our way and we can start foundations as soon as possible so make sure that you're sequencing the work right out of the gate to go fast and that you're able to mobilize quick and get going cuz this is is where we can gain time that is done with a pull plan now the other thing that I want to talk about is setting up the team when you're on your project site you want to get the job site trailer and your permanent team up and running as quickly as you can so power so the trailer and you might have
7:44 to have state inspection on that power Communications Furniture you know your Kawasaki mules whatever you need to get back and forth you want your command posts as far forward as possible towards the Battlefront as humanly possible is what Patton said and it construction what that means is we need to minimize the amount of time that it takes the management to get to the site to lead the work and enable and support the trade Partners so get your team set up do not fall asleep on getting this trailer on site the last one I want to talk about is the trade partner preparation process this process is your buyout okay and I'm just going to abbreviate these cuz I've talked about these before and I'll link you to the videos about the trade partner preparation process so buy out your pre-mobilization meeting your preconstruction meeting or
8:31 your prep meeting right and then there's three other steps okay I don't need to go through those right now but these are critical I want to see that all of these activities have the right buyout pre-mobilization and then the Preparatory preconstruction meeting happening at the right times ahead of the activities by 3 weeks so that they are ready to hit the ground running and they're not going to be on treasure hunts they're not going to be confused they're not going to wonder what's going on procurement temp utilities survey sequence the mobilization to hit the ground running set up the team and make sure you're following the trade partner preparation process this is how we really manage that project site early on and what I'm going to do is turn this into a canva graphic for you turn it
9:16 into a blog post and we're going to link you to the other videos about the trade partner preparation process this is going to be a series of videos of how to manage a construction site at different phases we'll link you to those too but I really hope you've enjoyed enjoy this content on we go