How Long Does A Kitchen Remodel Take? Tampa Kitchen Remodel Contractor Explains A Kitchen Timeline.
Video by Home Love Construction · 1 moment used in Oak Valley Designs's DIY guides · 8:26 long

Moments in this video
- 3:16–3:29 Inspections Phase
From How to Plan a Stair Remodel Budget and Sequence, Step 9: Schedule Inspections
After all the new internal systems (plumbing, electrical, HVAC) have been installed during the rough-in phase, the local county inspectors will conduct necessary checks. These inspections ensure that all work adheres to current building codes and matches the approved plans. This inspection process typically takes about 1 week. Passing these inspections is mandatory before moving on to the finishing stages of the renovation.
The guide that use this video
Transcript
0:01 hey what up it's brad with home love construction and today i want to explain a question that that literally we get asked all the time and that's how long does a kitchen renovation actually take how long does it take how long am i going to be without my kitchen living in a construction site oh my god how am i gonna do it just kidding that's not you obviously but seriously a lot of people are really concerned when they go into a kitchen renovation of like how long am i literally going to be living in a dusty dirty construction zone well let me let me first off say that uh when you're doing a kitchen renovation what we do is you if you walk into a kitchen renovation of ours you should be seeing you know dust bears you should be seeing zip walls all that kind of stuff like it should be like a clean area obviously there's still always dust like a construction zone i mean inside of a house a renovation dust just goes
0:48 everywhere like immediately like we step in the house we could be doing the estimate we step in the house and poof your house is like instantly dusty is what it seems like but we do a lot to keep the dust contained so let me just start with that but that said the question of timeline is really important because you have to plan your life around it and a lot of times the kitchen goes into other things so you may even have a pod where you're storing a lot of your furniture to keep it from getting dusty you know if you've got the restoration hardware if you've got the cloud couch like that thing needs to be put away while we're doing this because dust is going to get into it you know you can vacuum it out but you'll be having dust coming out of it for a long time so all that to say the timeline is important so let me actually tell you what the timeline looks like so the the kitchen renovation has kind of like a couple stages right so the first stage is planning and permitting so in
1:36 and i'm going to speak for the tampa bay area of florida which is our our primary service area that's that's really where we live and work so in the tampa bay area of florida a kitchen planning and and permitting timeline it usually takes between six to eight weeks maybe ten if there's a high volume of permits in in the permitting department so maybe to be safe maybe let's call it six to ten weeks right basically two months for like for lack of more clarity right it takes about two months to get your permit and that's just kind of run-of-the-mill whatever so nothing is actually happening during that two-month period it's actually illegal for us to start before we have that permit so we're pretty strict on not starting until we have that permanent hand then once we have the permit then a week or two later we actually start we don't always know when the permit's going to come out so it's a
2:21 bit of a mystery so our our demo crew is not ready the next day so we have to wait we there's a little bit of a gap there where it's like we got the permit okay call the demo crew get them on so that is a little bit of a added delay there but unfortunately it's the nature of the beast so from there we have demolition and our rough-in trades usually this is about a two to three week process where you're actually gutting the existing kitchen pulling up the flooring all that kind of stuff and then putting your new guts back into your kitchen this is two or three weeks realize that in a large major kitchen renovation this could be a four week process if you're having to run a lot of electrical lines back to the panel and your electricians are there for a week and no one else can be there because they're all in the way and stuff and your hvac guy can't get in between the wires that could that could lose a week
3:07 you know of of hard work it could it could eat up a week of your timeline so realize that call it two to four weeks for the demo and rough-in phase then you're gonna have a week of what are basically inspections from the county where they're going to come in and say okay was all this done correctly then they're going to come and check all that off right so there's a week's an hour up to about five weeks of actual construction on the high end then we go into uh the the start of the what we call like the refinishing phase so at that point if you did a trench like to bring your electrical or plumbing out to your island you got to fill it in with concrete the walls have to be insulated and recovered with drywall then the walls all have to be painted so that process of getting the drywall and the paint and all that all done before the cabinets even get looked at is
3:52 another two week process because you got to go and do it and then you got to figure out you know where all your drywall touch-ups boom get all the drywall texture done then you have your paint where all your paint touch up spoon get all the paint perfect and then you have your actual cabinet install at that point you can install your cabinets now i'll say there is kind of a branch a fork in the road here between different types of flooring if you're doing a floating floor you do not i will say again you do not put cabinets on top of a floating floor any cabinet supplier floor manufacturer will tell you this you don't put cabinets on top of a floating floor so if you're doing a vinyl or a you're doing a luxury vinyl or a laminate like a waterproof laminate floor you do that up to the cabinet so you set the cabinets first so now you're going to have about a call it three to four week phase
4:39 of cabinet installation the little like finishing things and the flooring installation all that lump together is maybe three to four weeks okay so now we're up to let's say boom plus another two to three weeks for the drywall eight plus these four so now you're up to actually 12 weeks of actual construction time stay with me here but now you're close you're like close to the end at this point once the cabinets are down you get your countertops templated and you that's where they come in and literally measure the exact cabinet layouts like they can't just come and drop a slab of granite or quartz on your countertops they have to measure to the exact you know eighth of an inch exactly what the distance from the wall is so that the reveal is exactly the same all the way across your granite that's how they make it look so perfect is they don't do it until the cabinets are actually set and
5:25 in place very very important to not do it until then so they come in and they template now you're going to have a week or two gap between the template and actually while the cutting is going on at the shop they pull the slabs they cut it they do all the edge finishing then they bring it back a week or two later and actually install it now we're up to 13 weeks we have a week for backsplash and trim outs and then we're actually done and we put our appliances in so if you take all that together we're now between 14 and 18 weeks of a kitchen renovation so what does that break down to that breaks down to three and a half to four and a half months is the real timeline of construction for a kitchen renovation done the right way and we're talking about luxury kitchen renovations here we're not talking about i just want to reface my cabinets or i just want to refinish my countertops
6:11 you know this is like got my kitchen i hate the way it was done previously i have a 1970s kitchen you know on the beach in reddington shores or something and uh i i just hate it just got the whole thing and give me a complete new one that's what we're talking about here obviously if you're doing a reface that's a couple weeks like replacing your countertops a couple weeks this is a this is a really all out kitchen renovation but realistically the actual timeline is between three to four and a half months like realistically on the smaller side maybe down maybe you could get a hair lower than that if you really got everybody stacked up but what we find is that with little fixes and the things that you know have to be taken care of and like little call backs there's always little callbacks what we find is three to four and a half months is realistic for kitchen renovation
6:58 so that said if you're still up for it after all that and you're in the tampa bay area i want to do your kitchen renovation i want my team that you know that right there i want our team to be doing your kitchen renovation so send us an email to homelove construction gmail.com or go to our website which is homelove.construction or just put in a google home love construction the website will be the first thing that pops up we have a get a quote form on there you can just go in boom put in your information i actually have a video there explaining exactly what we do with that information i shot that sitting on my parents table funny enough and it explains exactly what happens with your your information so that you know what's going on the whole step of the way so if that's you you have a kitchen
7:44 renovate renovation in the tampa bay area that you need a contractor for and you want the best contractor to do it just send us an email the rest will be taken care of thank you for watching i do really appreciate it if you have not already be sure you subscribe to our youtube channel it helps us a lot it helps me a lot i'm personally asking you please subscribe it does help us a ton subscribe to our youtube like us on facebook we're home love construction at both of those places see you in the next video let me know what you thought in the comments we'll talk to you very soon peace
Automatically transcribed from the source video.