Step 2 · Install Drainage and Gravel Base

After excavating, add a layer of coarse gravel (e.g., 3/4-inch crushed stone) to the bottom of the excavated area, about 4-6 inches deep. This layer is crucial for proper drainage, preventing water from pooling under the steps and causing frost heave or erosion. Compact this gravel layer thoroughly using a tamper. Add a thinner layer (about 1-2 inches) of smaller gravel or coarse sand on top of the compacted coarse gravel.

Tools and Materials

Plunger Level Husky 6 cu. ft. Steel Wheelbarrow with Flat Free Tire Yard Elements 25 Cu. Ft. of Small 3/4 in. Clean Crushed Gravel Bulk Landscape Rock and Pebble for Gardening, Landscaping and Walkways Quikrete 70 lb. All-Purpose Sand 115270